An acceptable prototype does not automatically guarantee a stable production batch. First-article inspection creates a clear approval point for the drawing, material, process and critical dimensions before volume increases.

Lock the correct drawing revision

Before production, confirm the part number, revision, material, finish and quantity. The shop and inspection room must use the same customer-approved revision.

Identify critical dimensions

Not every dimension carries the same risk. Locating datums, mounting holes, mating surfaces, flatness and function-controlling features should receive priority.

Record traceable measurement results

Identify the first article and record values, instruments, date and inspector. Part photos and measurement locations help both sides resolve differences quickly.

Release the batch only after confirmation

After approval, parameters and control points move into in-process inspection. If the first article fails, correct the program, fixture or measurement method before producing more parts.